The Harbour by Eagle Hills is sold on a 50/50 plan: half of the price is paid in eight steps while the buildings rise, and half on handover, scheduled for December 2028. This guide lists every instalment with its milestone, indicative date and amount for each apartment size.
The schedule
| Milestone | Indicative date | Payment | Cumulative |
|---|---|---|---|
| Down payment (SPA signing) | On booking | 10% | 10% |
| Substructure completion | March 2027 | 5% | 15% |
| Superstructure 50% | June 2027 | 5% | 20% |
| Superstructure 100% (topping out) | October 2027 | 5% | 25% |
| Façade completion | April 2028 | 5% | 30% |
| Construction progress | June 2028 | 10% | 40% |
| Construction completion | October 2028 | 10% | 50% |
| Handover | December 2028 | 50% | 100% |
Construction instalments are linked to milestones, not to the calendar. The dates are the developer's indicative targets: if a milestone is reached earlier or later, the instalment moves with it.
What you pay at each starting price
| Instalment | 1 bedroom | 2 bedroom | 3 bedroom |
|---|---|---|---|
| Down payment (SPA signing) (10%) | AED 269,889 | AED 354,689 | AED 635,289 |
| Substructure completion (5%) | AED 134,944 | AED 177,344 | AED 317,644 |
| Superstructure 50% (5%) | AED 134,944 | AED 177,344 | AED 317,644 |
| Superstructure 100% (topping out) (5%) | AED 134,944 | AED 177,344 | AED 317,644 |
| Façade completion (5%) | AED 134,944 | AED 177,344 | AED 317,644 |
| Construction progress (10%) | AED 269,889 | AED 354,689 | AED 635,289 |
| Construction completion (10%) | AED 269,889 | AED 354,689 | AED 635,289 |
| Handover (50%) | AED 1,349,444 | AED 1,773,444 | AED 3,176,444 |
| Total during construction (50%) | AED 1,349,444 | AED 1,773,444 | AED 3,176,444 |
At the 1 bedroom starting price of AED 2,698,888, the down payment on signing is AED 269,889, and the remaining AED 1,079,555 of the construction share is spread across seven milestones over about twenty months.
Why a 50/50 plan suits this launch
- Half the price stays in your hands until the keys are ready, which keeps the cash committed during construction lower than on a 60/40 or 70/30 plan.
- The handover payment can be financed with a mortgage once the building is complete, subject to bank approval at the time.
- A 10% down payment secures the unit at launch pricing, before any later release is priced.
Fees to plan for
Alongside the purchase price, buyers in Abu Dhabi typically budget for the registration fee charged by the authorities and any administration fees set by the developer. Your Obaco Homes advisor confirms the current amounts before you book.
Dates are indicative. Prices, availability and dates are subject to change without notice. Figures on this page are for guidance only and are not an offer.
What is the down payment for The Harbour?
The down payment is 10% of the price, paid on signing the sale and purchase agreement. At the published starting prices that is AED 269,889 for a 1 bedroom apartment, AED 354,689 for a 2 bedroom and AED 635,289 for a 3 bedroom.
How much is paid on handover?
50% of the price is paid on handover, scheduled for December 2028.
Can I use a mortgage for the handover payment?
Yes, the handover payment is usually financed with a mortgage once the building is complete, subject to the bank's approval at that time. An Obaco Homes advisor can introduce mortgage options.